Dataset Viewer
Auto-converted to Parquet Duplicate
iso
string
queue_id
string
project_name
string
state
string
fuel
string
mw
float64
queue_date
string
current_cod
string
status_raw
string
years_in_queue
float64
studies_complete
bool
ia_executed
bool
stall_flags
int64
CAISO
1402
ATLAS COMPLEX
AZ
Battery
3,200
2017-05-01
2028-03-31
ACTIVE / IA Executed
9.51
true
true
1
PJM
AE1-070 - moved to TC1
Elwood 345 kV
IL
Natural Gas
1,610
2018-07-31
2020-12-31
Active
8.27
true
false
2
CAISO
1889
HOLMAN
CA
Battery
1,500
2021-04-15
2034-02-17
ACTIVE / IA Executed
5.56
true
true
1
CAISO
1632
SANBORN HYBRID 3
CA
Battery
1,400
2019-04-15
2026-12-31
ACTIVE / IA Executed
7.56
true
true
1
NYISO
C24-003
Vineyard Mid-Atlantic West
NY
OSW
1,321
2024-08-01
2031-08-01
NYISO status 7.0
2.26
true
false
1
NYISO
C24-021
Bluepoint Wind 1
NY
OSW
1,310
2024-08-01
2033-12-01
NYISO status 7.0
2.26
true
false
1
PJM
AE1-105
Maidsville CCGT (North Longview 500 kV)
WV
Natural Gas
1,270
2018-09-06
2026-07-01
Suspended
8.17
true
true
2
PJM
AF2-034 - moved to TC1
Kendall 345kV
IL
Solar; Storage
1,238.8
2019-10-28
2021-06-01
Active
7.03
true
false
2
PJM
AE2-152
Loretto-Wilton & Braidwood-Davis Creek
IL
Solar
1,150
2019-03-04
2020-09-30
Active
7.68
true
false
2
CAISO
1625
ANGELENO SOLAR FARM
CA
Battery
1,150
2019-04-15
2028-12-31
ACTIVE / IA Executed
7.56
true
true
1
CAISO
1943
WINGTIP SOLAR 1
CA
Solar
1,150
2021-04-15
2032-09-18
ACTIVE / IA Executed
5.56
true
true
1
PJM
AG1-004
Grange Solar (Marysville-Sorenson 765 kV)
OH
Storage
1,100
2020-04-20
2023-12-31
Active
6.55
true
false
2
MISO
J2186
Ipava-Maple Ridge 345kV (4573)
IL
Solar
820.6
2022-06-22
2024-10-01
Active Post-Phase 3 Not Started
4.37
true
true
1
MISO
J2846
Reynolds--Burr Oak 345kV line
IN
Solar
700
2022-09-15
2025-12-01
Pending Revision Approval Phase 3 Not Started
4.14
true
true
1
MISO
J3084
Merom (HED) - Dresser 345.0kV
IN
Gas
641.8
2025-08-12
2026-01-01
Pending Revision Approval Phase 3 Not Started
1.23
true
true
1
ERCOT
26INR0546
Hobby BESS I
TX
OTH BA
602.56
2024-09-04
2028-10-21
SS Completed, FIS Completed, No IA
2.17
true
false
1
ERCOT
25INR0632
Jenna Eco-Electric Solar
TX
SOL PV
576.3
2024-05-20
2029-04-16
SS Completed, FIS Completed, No IA
2.46
true
false
1
MISO
J3075
Merom Primary - Worthington Primary 345.0kV
IN
Hybrid
560
2022-09-15
2025-11-30
Pending Revision Approval Phase 3 Not Started
4.14
true
true
1
ERCOT
27INR0115
Diamante BESS
TX
OTH BA
513.68
2024-02-27
2028-11-01
SS Completed, FIS Completed, No IA
2.69
true
false
1
SPP
GEN-2021-030
Evergy Tap the La Cygne to Stillwel 345 kV Line
KS
null
510.3
2021-05-14
2029-12-31
IA FULLY EXECUTED/ON SUSPENSION
5.48
true
true
1
ERCOT
28INR0132
River Boat Solar
TX
SOL PV
502.2
2024-09-04
2029-04-21
SS Completed, FIS Completed, No IA
2.17
true
false
1
ERCOT
26INR0230
Titus Sienta Solar
TX
SOL PV
501.93
2023-10-13
2029-04-19
SS Completed, FIS Completed, No IA
3.07
true
false
1
MISO
J2171
Aster to Commodore
IL
Solar
500
2022-03-25
2024-05-01
Active Post-Phase 3 Not Started
4.62
true
true
1
SPP
ERAS-2025-009
Grec #1 Interconnect 161kV Substation
OK
Coal
450
2025-10-01
2026-10-01
IA FULLY EXECUTED/ON SCHEDULE
1.1
true
true
1
NYISO
1080
Mineral Basin Solar Power
PA
S
401.6
2020-08-21
2029-12-01
NYISO status 10.0
6.21
true
false
2

Stalled Interconnection Queue Projects: free sample (Tensorust LLC)

Every active generation request in six U.S. grid queues, with the ones that are stuck flagged and why.

Headline: Six grid operators (PJM, MISO, ERCOT, SPP, CAISO, NYISO) hold 6,904 active generation requests totaling 1,390.5 GW, and 2,570 of them (427.3 GW) are stuck by at least one rule: studies done with no agreement after 2+ years, an agreement signed but the online date slipped 2+ years or already passed, suspended, or 5+ years in queue with no agreement.

This repository is a free teaser, not the dataset. It holds 25 example rows and a summary table with no names in it. The full file has 6,904 rows and is sold by Tensorust LLC: https://tensorust.com/datasets/interconnection-queue-stalled/.

Files here

file what it is
sample.csv 25 rows of the full file (the same sample shown on tensorust.com)
summary_by_iso.csv row counts and totals by ISO across the full file, no entity names (groups with fewer than 3 rows are folded into "Other")

Summary by ISO (largest groups)

ISO rows Capacity (MW)
PJM 2,799 418,039
ERCOT 1,736 445,898
MISO 1,194 277,249
SPP 678 139,200
CAISO 261 73,848
NYISO 236 36,287
TOTAL 6,904 1,390,521

Full table: summary_by_iso.csv.

What the full file has

  • 6,904 rows
  • Key fields: iso, queue_id, project_name, developer, state, county, poi, transmission_owner, fuel, mw
  • Parquet and CSV, a README with sources, method and limits, and the build script
  • Free 25-row sample (no personal contact data)

Coverage: Active generation requests: PJM 2,799, ERCOT 1,736, MISO 1,194, SPP 678, CAISO 261, NYISO 236. Operator queue files fetched Nov 6 2026; built Nov 6 2026

Columns in the full file

column meaning
iso Grid operator
queue_id Operator queue number
project_name Project or point of interconnection name
developer Developer or interconnection customer (ERCOT and NYISO only)
state State
county County
poi Point of interconnection
transmission_owner Transmission owner
fuel Fuel or technology as the operator lists it
mw Requested MW
queue_date Date the request entered the queue
original_cod Original commercial operation date where published
current_cod Current commercial operation date
status_raw Operator status text
studies_complete Final or system impact studies complete
ia_executed Interconnection agreement executed
suspended Operator lists the project as suspended
under_construction Under construction or in engineering and procurement
delay_cause Operator's stated cause of delay (SPP only)
years_in_queue Years from queue date to the build date
cod_slip_years Current COD minus original COD, years
flag_studies_done_no_ia Studies complete, no agreement, 2+ years in queue
flag_ia_signed_cod_slipped Agreement signed, not under construction, COD slipped 2+ years or already passed
flag_suspended Suspended
flag_aged_no_ia 5+ years in queue with no agreement
stall_flags Number of flags set
stalled At least one flag set
late_stage Studies complete or agreement executed
developer_oid Tensorust ontology organization id for the developer
developer_sources Public sources the developer appears in
developer_federal_awards_fy25plus Developer's federal awards FY2025 on, USD (ontology)

Get the full file

tier price includes
One grid operator $900 Every active request in one ISO with stall flags, MW, dates and status, sorted for late-stage stalled projects. CSV and Excel.
Six-ISO file $3,900 All 6,904 requests across PJM, MISO, ERCOT, SPP, CAISO and NYISO in one schema, with stall flags and developer links where published.
Monthly stall tracker $12,000 a year The six-ISO file re-run monthly, with newly stalled, newly withdrawn and newly signed projects marked, for origination and M&A teams. Internal use, unlimited seats.

Email mattbusel@tensorust.com with the tier and a billing contact, and we will send a proper invoice (ACH or card). The file is delivered once the invoice is paid. Details and the live sample: https://tensorust.com/datasets/interconnection-queue-stalled/. All datasets: https://tensorust.com/datasets/

Method and limits

Download each operator's public queue file (PJM planning queue XML, MISO GI queue API, ERCOT GIS report, SPP active queue CSV, CAISO public queue report, NYISO queue workbook), keep active generation requests, map each operator's status fields to studies_complete, ia_executed, suspended and under_construction, compute years in queue and COD slip against the build date, set the four stall flags, and join developer names (published only by ERCOT and NYISO) to the Tensorust ontology. LBNL's Queued Up compilation sits behind an interactive challenge page, so the operator files are used directly.

Not every U.S. queue (ISO-NE and non-ISO utilities are not in it), not a forecast of withdrawals, and not developer data for PJM, MISO, SPP or CAISO (those operators do not publish it). Flag rates differ by operator because each publishes different fields: CAISO and MISO publish agreement status and online dates on nearly every project, PJM publishes queue age, so compare within an operator first.

Sources

License

The sample and summary here are free to view, analyze and cite with attribution to "Tensorust LLC, https://tensorust.com/datasets/interconnection-queue-stalled/". The full dataset is licensed separately per tier. No resale or redistribution of Tensorust data without a written license.

Tensorust LLC, Tuckahoe NY. mattbusel@tensorust.com | https://tensorust.com