tensorust-studio's picture
Free teaser: 25-row sample + aggregate summary
86dac57 verified
|
Raw History Blame Contribute Delete
7.33 kB
metadata
license: other
license_name: tensorust-sample-license
license_link: https://tensorust.com/datasets/interconnection-queue-stalled/
pretty_name: Stalled Interconnection Queue Projects (free sample)
language:
  - en
tags:
  - tensorust
  - sample
  - energy
  - government-data
  - finance
size_categories:
  - n<1K
configs:
  - config_name: sample
    data_files:
      - split: train
        path: sample.csv
  - config_name: summary
    data_files:
      - split: train
        path: summary_by_iso.csv

Stalled Interconnection Queue Projects: free sample (Tensorust LLC)

Every active generation request in six U.S. grid queues, with the ones that are stuck flagged and why.

Headline: Six grid operators (PJM, MISO, ERCOT, SPP, CAISO, NYISO) hold 6,904 active generation requests totaling 1,390.5 GW, and 2,570 of them (427.3 GW) are stuck by at least one rule: studies done with no agreement after 2+ years, an agreement signed but the online date slipped 2+ years or already passed, suspended, or 5+ years in queue with no agreement.

This repository is a free teaser, not the dataset. It holds 25 example rows and a summary table with no names in it. The full file has 6,904 rows and is sold by Tensorust LLC: https://tensorust.com/datasets/interconnection-queue-stalled/.

Files here

file what it is
sample.csv 25 rows of the full file (the same sample shown on tensorust.com)
summary_by_iso.csv row counts and totals by ISO across the full file, no entity names (groups with fewer than 3 rows are folded into "Other")

Summary by ISO (largest groups)

ISO rows Capacity (MW)
PJM 2,799 418,039
ERCOT 1,736 445,898
MISO 1,194 277,249
SPP 678 139,200
CAISO 261 73,848
NYISO 236 36,287
TOTAL 6,904 1,390,521

Full table: summary_by_iso.csv.

What the full file has

  • 6,904 rows
  • Key fields: iso, queue_id, project_name, developer, state, county, poi, transmission_owner, fuel, mw
  • Parquet and CSV, a README with sources, method and limits, and the build script
  • Free 25-row sample (no personal contact data)

Coverage: Active generation requests: PJM 2,799, ERCOT 1,736, MISO 1,194, SPP 678, CAISO 261, NYISO 236. Operator queue files fetched Nov 6 2026; built Nov 6 2026

Columns in the full file

column meaning
iso Grid operator
queue_id Operator queue number
project_name Project or point of interconnection name
developer Developer or interconnection customer (ERCOT and NYISO only)
state State
county County
poi Point of interconnection
transmission_owner Transmission owner
fuel Fuel or technology as the operator lists it
mw Requested MW
queue_date Date the request entered the queue
original_cod Original commercial operation date where published
current_cod Current commercial operation date
status_raw Operator status text
studies_complete Final or system impact studies complete
ia_executed Interconnection agreement executed
suspended Operator lists the project as suspended
under_construction Under construction or in engineering and procurement
delay_cause Operator's stated cause of delay (SPP only)
years_in_queue Years from queue date to the build date
cod_slip_years Current COD minus original COD, years
flag_studies_done_no_ia Studies complete, no agreement, 2+ years in queue
flag_ia_signed_cod_slipped Agreement signed, not under construction, COD slipped 2+ years or already passed
flag_suspended Suspended
flag_aged_no_ia 5+ years in queue with no agreement
stall_flags Number of flags set
stalled At least one flag set
late_stage Studies complete or agreement executed
developer_oid Tensorust ontology organization id for the developer
developer_sources Public sources the developer appears in
developer_federal_awards_fy25plus Developer's federal awards FY2025 on, USD (ontology)

Get the full file

tier price includes
One grid operator $900 Every active request in one ISO with stall flags, MW, dates and status, sorted for late-stage stalled projects. CSV and Excel.
Six-ISO file $3,900 All 6,904 requests across PJM, MISO, ERCOT, SPP, CAISO and NYISO in one schema, with stall flags and developer links where published.
Monthly stall tracker $12,000 a year The six-ISO file re-run monthly, with newly stalled, newly withdrawn and newly signed projects marked, for origination and M&A teams. Internal use, unlimited seats.

Email mattbusel@tensorust.com with the tier and a billing contact, and we will send a proper invoice (ACH or card). The file is delivered once the invoice is paid. Details and the live sample: https://tensorust.com/datasets/interconnection-queue-stalled/. All datasets: https://tensorust.com/datasets/

Method and limits

Download each operator's public queue file (PJM planning queue XML, MISO GI queue API, ERCOT GIS report, SPP active queue CSV, CAISO public queue report, NYISO queue workbook), keep active generation requests, map each operator's status fields to studies_complete, ia_executed, suspended and under_construction, compute years in queue and COD slip against the build date, set the four stall flags, and join developer names (published only by ERCOT and NYISO) to the Tensorust ontology. LBNL's Queued Up compilation sits behind an interactive challenge page, so the operator files are used directly.

Not every U.S. queue (ISO-NE and non-ISO utilities are not in it), not a forecast of withdrawals, and not developer data for PJM, MISO, SPP or CAISO (those operators do not publish it). Flag rates differ by operator because each publishes different fields: CAISO and MISO publish agreement status and online dates on nearly every project, PJM publishes queue age, so compare within an operator first.

Sources

License

The sample and summary here are free to view, analyze and cite with attribution to "Tensorust LLC, https://tensorust.com/datasets/interconnection-queue-stalled/". The full dataset is licensed separately per tier. No resale or redistribution of Tensorust data without a written license.